| Phase | Estimated Duration |
| Corporate Bank Account Opening | 2-4 weeks |
| Business License Applications (if applicable) | 4-12 weeks |
| Office Search & LOI | 2-6 weeks |
| Tenancy Agreement Finalization | 1-2 weeks |
| Design Development & Drawings | 2-4 weeks |
| Authority Submission & Approval | 3-8 weeks |
| Renovation Works | 4-10 weeks |
| Total Estimated Duration | 3-6 months |






.png)
.png)
| Authority | Purpose |
| Building Management | Fit-out compliance |
| Local Council | Structural & renovation approval |
| Fire Department (BOMBA) | Fire safety compliance |
| Authority | Timeline |
| Building Management | 1-2 weeks |
| Local Authority | 2-4 weeks |
| Fire Department | 2-6 weeks |
| Office Size | Duration |
| 2,000-3,000 sq ft | 4-6 weeks |
| 5,000-10,000 sq ft | 6-10 weeks |
| 10,000+ sq ft | 10-14 weeks |
| Cost Component | Estimated Range |
| Rental Deposit | 3-6 months rental |
| Renovation Cost | RM100-RM250 per sq ft |
| Professional Fees | RM20,000-RM100,000 |
| Authority Submission Fees | RM5,000-RM20,000 |