Installing a ceiling cassette unit requires precision to ensure proper drainage and aesthetics. This process typically follows these core steps:

1. Positioning & Preparation

  • Location: Choose a central area with no obstructions to airflow. Ensure the ceiling structure can support the unit's weight (often 20kg - 50kg).

  • Marking: Use the provided paper template to mark the ceiling cut-out and the four suspension bolt locations.

  • Cutting: Cut the ceiling opening slightly larger than the unit body but smaller than the decorative panel.

2. Suspension & Mounting

  • Bolts: Install four M10 or W3/8 suspension bolts into the concrete slab or reinforced wooden beams.

  • Hanging: Lift the indoor unit and secure it using double nuts and washers.

  • Leveling: Use a spirit level. The unit must be perfectly horizontal or slightly tilted toward the drain pipe (depending on manufacturer specs) to prevent water leakage.

3. Piping & Electrical

  • Refrigerant Lines: Connect the copper gas and liquid pipes using flare joints. Vacuum the system to remove moisture.

  • Drainage: Connect the drain hose. Cassette units usually have a built-in lift pump; ensure the external pipe has a downward slope of at least 1:100.

  • Wiring: Connect the power and communication cables between the indoor and outdoor units following the wiring diagram.

4. Finishing

  • Panel Installation: Attach the decorative grille (panel). Connect the display and swing-motor wires to the main control board.

  • Test Run: Operate the unit for 30 minutes. Check for abnormal noise, proper cooling/heating, and verify that the drain pump is discharging water correctly.