Malaysia to Launch 2.65GW LSS6 Solar Programme With 1.25GW Battery Storage

Malaysia to Launch 2.65GW LSS6 Solar Programme With 1.25GW Battery Storage

Solar100
Malaysia Solar News
Malaysia Energy Policy

Malaysia to Launch 2.65GW LSS6 Solar Programme with 1.25GW BESS

The sixth Large Scale Solar programme will offer 2,500MW of solar paired with 1,250MW of battery storage, together with a separate 150MW solar allocation for Bumiputera developers.

Solar100 Editorial Desk | Policy announced: 16 July 2026

According to information released by the Ministry of Energy Transition and Water Transformation (PETRA) , the programme is intended to expand renewable generation and support Malaysia's energy transition. A major change under LSS6 is the inclusion of Battery Energy Storage Systems, or BESS, under its two largest packages.

Key figures
  • Total solar capacity: 2,650MW;
  • BESS power under Packages 1 and 2: 1,250MW;
  • Estimated private investment: RM13 billion to RM15 billion;
  • Commercial operation target: no later than 31 December 2029.

Three tender packages

Package Solar BESS Participation
Package 1 2,200MW 1,100MW Open to eligible large-scale solar developers
Package 2 300MW 150MW Open tender for Bumiputera developers
Package 3 150MW Not required For smaller Bumiputera solar developers

Projects proposed under Packages 1 and 2 may range from 60MW to 500MW. Package 3 will cover smaller projects ranging from 10MW to 30MW.

Solar100 fact check
  • 2,500MW is the combined solar capacity under Packages 1 and 2;
  • Package 3 adds a separate 150MW solar-only allocation;
  • Total solar capacity is therefore 2,650MW or 2.65GW;
  • The 1,250MW BESS figure measures power, not energy capacity. PETRA has not yet stated the corresponding MWh capacity or storage duration.

Why battery storage is included

Solar output changes with sunlight, cloud cover and the time of day. BESS can store electricity during periods of higher solar production and release it when required by the power system, supporting grid flexibility and stability.

The number of hours a battery can supply electricity depends on its MWh capacity, operating strategy, system losses and grid requirements. The announced 1,250MW figure alone cannot be used to calculate storage duration.

Southern Malaysia and local manufacturing

LSS6 will prioritise strategic locations experiencing rapid electricity-demand growth, particularly southern Peninsular Malaysia. This is relevant to Johor, where data centres, advanced manufacturing and industrial development are increasing power demand.

PETRA also said priority will be given to projects using renewable-energy products manufactured in Malaysia, including locally produced photovoltaic modules. The precise requirements will depend on the technical and evaluation criteria in the official Request for Proposal documents.

Investment, jobs and RFP schedule

PETRA projects that LSS6 could attract RM13 billion to RM15 billion in private investment, create about 15,000 to 20,000 jobs during development and construction, and reduce carbon dioxide emissions by approximately 2.6 million tonnes annually.

These are government projections based on successful programme implementation, not outcomes that have already been achieved.

  • Packages 1 and 2 RFP documents: 27 July to 7 August 2026;
  • Package 3 RFP documents: 17 to 28 August 2026.

These dates refer to the announced periods for obtaining the relevant RFP documents. Companies should consult the Energy Commission's official documents for eligibility conditions, purchasing procedures and final submission deadlines.

Does LSS6 apply to rooftop solar?

No. LSS6 is a competitive programme for large-scale power plants. It is not a residential rebate and does not replace Solar ATAP or SuRIA Home. It is also separate from a standard commercial rooftop installation for a factory, shop, office or warehouse.

Frequently asked questions

Does 1,250MW of BESS mean 1,250MWh?

No. MW measures charging or discharging power, while MWh measures the amount of energy stored.

Have LSS6 projects started generating electricity?

No. The programme is entering the tender stage. Projects must complete approvals, financing, construction, grid connection and commissioning before operation.

For information about commercial solar or battery storage solutions in Malaysia, contact Solar100.

Contact Solar100 on WhatsApp

Sources

  • Ministry of Energy Transition and Water Transformation Malaysia (PETRA), LSS6 policy statement, 16 July 2026. View PETRA media statements
  • The Vibes, “PETRA unveils LSS6 solar initiative with 2,500MW capacity to boost renewable energy transition”, 16 July 2026. View the cross-checked report
  • Business Today, “Govt Set To Launch LSS6 With Up To 500MW Packages”, 16 July 2026. View the programme details

This article was independently prepared by Solar100 using publicly available information from PETRA and reliable news sources. It is provided for general energy information only and does not constitute tender, investment, legal, financing, engineering or eligibility advice. Participation requirements should be verified against the official RFP documents issued by the Energy Commission of Malaysia.